A claimant other than a direct contractor may not enforce a lien unless the claimant records a claim of lien within the following times:

(a) After the claimant ceases to provide work.

(b) Before the earlier of the following times:

(1) Ninety days after completion of the work of improvement.

(2) Thirty days after the owner records a notice of completion or cessation.

Notes and commentary — not statutory text

History

Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.

Source of truth

Edition
As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
Official file
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=CIV&sectionNum=8414.
Text hash
sha256 56e2e5ee77318b6ec591765a58e48078529f3dfde7bf1bbd7d19f802a16fbd7a
Composed by
compose_ca.py 2026-10-22: the Legislative Counsel's CAML content files read by a tokenizer (caml_readers.reader_a); an independent xml.etree reading (caml_readers.reader_b) agrees on every section

Cited by 2 provisions

Provisions in this library whose text cites Civ. Code, § 8414. Each shows the citation as that text prints it.

Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.