(a) The estimated costs of a project for which an application is submitted shall be consistent with normal public construction costs in the applicant’s area.

(b) An applicant wishing to construct a project having costs that exceed normal public construction costs in the area may apply for a grant in an amount not to exceed 65 percent of the normal costs up to a maximum of twenty million dollars ($20,000,000) per project if the applicant certifies that it is capable of financing the remainder of the project costs from other sources.

Notes and commentary — not statutory text

History

Added by Stats. 1999, Ch. 726, Sec. 1. Approved in Proposition 14 at the March 7, 2000, election.

Source of truth

Edition
As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
Official file
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=EDC&sectionNum=19996.
Text hash
sha256 7ffc17d1ea11743055945bbe356000b887c2aa9f5080fdf9ce7d6e7ce964885b
Composed by
compose_ca.py 2026-10-22: the Legislative Counsel's CAML content files read by a tokenizer (caml_readers.reader_a); an independent xml.etree reading (caml_readers.reader_b) agrees on every section

Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.