Gov. Code, § 14556.18 · Article 3. Fund Allocation and Expenditure
Gov. Code, § 14556.18
Text — As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
(a) Commission approval of a project application establishes the time schedule, by fiscal year, for implementation of the phases of a project. Project approval shall be deemed rescinded if the lead applicant agency or the agency responsible for carrying out the project does not seek an allocation from the commission and start the first phase of work during the fiscal year scheduled.
(b) If the first phase is not completed as scheduled, so that work on subsequent phases is delayed, the agency responsible for carrying out the project shall report the reasons for failure to complete the project to the commission. The commission may then reconsider the project application, ask for modification of the schedule and any other requirements of the application, and may, at its discretion, extend the time of reconsideration until environmental studies, review, and approval of final environmental documents has been completed.
Notes and commentary — not statutory text
History
Added by Stats. 2000, Ch. 91, Sec. 6. Effective July 7, 2000.
Source of truth
- Edition
- As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
- Official file
- https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV§ionNum=14556.18.
- Text hash
- sha256 9a6868779d6c8a0a1227a8b7e35ebb1f90022cbdd98d8dd2e73fcf6afd280afa
- Composed by
- compose_ca.py 2026-10-22: the Legislative Counsel's CAML content files read by a tokenizer (caml_readers.reader_a); an independent xml.etree reading (caml_readers.reader_b) agrees on every section
Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.