Gov. Code, § 14556.28 · Article 4. Administration and Expenditure of Funds
Gov. Code, § 14556.28
Text — As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
(a) For applicants other than the department, funds allocated shall generally be administered as a reimbursement program. At the request of an applicant, the commission shall authorize an advance payment for project development work necessary for a project specified in Article 5 (commencing with Section 14556.40). At the request of an applicant, the commission may authorize an advance payment for demonstrated need, or for a project right-of-way, construction, or procurement phase.
(b) Project costs incurred prior to commission approval of a project application may not be reimbursed. Project costs incurred prior to commission allocation of funds, but after commission approval of a project application, may be reimbursed retroactively after allocation.
Notes and commentary — not statutory text
History
Added by Stats. 2000, Ch. 91, Sec. 6. Effective July 7, 2000.
Source of truth
- Edition
- As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
- Official file
- https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV§ionNum=14556.28.
- Text hash
- sha256 53f2bf2371f39e27c104682a87032050a60af502a462c35b5de14b9613e626f0
- Composed by
- compose_ca.py 2026-10-22: the Legislative Counsel's CAML content files read by a tokenizer (caml_readers.reader_a); an independent xml.etree reading (caml_readers.reader_b) agrees on every section
This section cites
Provisions in this library that the text above cites, as it prints each citation. A range cited as “ss. 61.13-61.16” links its first and last provisions.
Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.