(a) Prior to seeking the State Public Works Board establishment of the scope and cost, the Judicial Council shall submit a report to the Joint Legislative Budget Committee describing the scope, budget, schedule, number of courtrooms, number of secure holding cells, and square footage of administrative support space to be constructed or renovated. If the Joint Legislative Budget Committee fails to take any action with respect to each report within 30 days after submittal, this inaction shall be deemed to be approval for the purposes of this section, and the Judicial Council is authorized to proceed to acquire real property and complete preliminary plans.

(b) (1) Upon certification of the availability of funds within the State Court Facilities Construction Fund and the establishment of the project scope and cost by the State Public Works Board, notwithstanding any other provision of law, the Judicial Council is authorized to acquire real property and to complete preliminary plans for the superior court capital outlay projects adopted by the Judicial Council on October 24, 2008, identified in the Update to Trial Court Capital-Outlay Plan and Prioritization Methodology, or most recent version thereof.

(2) It is the intent of the Legislature that funding for working drawings and construction be appropriated in the next annual Budget Act following approval by the State Public Works Board of preliminary plans completed pursuant to paragraph (1).

(3) The scope and cost of the projects, including augmentations, authorized by this section shall be subject to approval and administrative oversight by the State Public Works Board pursuant to Section 13332.11 or 13332.19. For purposes of this section, the availability of an augmentation for each individual project shall be calculated based on the total capital outlay cost as established by the board.

(c) (1) The Judicial Council shall submit to the Senate Committee on Budget and Fiscal Review and the Assembly Committee on Budget a long-term fund condition statement for the State Court Facilities Construction Fund in conjunction with any future funding request for capital outlay to demonstrate that there is sufficient revenue to fully support all existing debt or capital outlay obligations as well as the full project cost for the proposed project for which the Judicial Council requests funding.

(2) This subdivision shall not apply to a capital outlay request pertaining to the construction of the new court facility projects approved in the Budget Act of 2018.

Notes and commentary — not statutory text

History

Amended by Stats. 2021, Ch. 79, Sec. 19. (AB 143) Effective July 16, 2021.

Source of truth

Edition
As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
Official file
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=70371.7.
Text hash
sha256 929e72d4e567d95843b5f41653b4e162e501729fd93d6bb736de335a5b0dac5e
Composed by
compose_ca.py 2026-10-22: the Legislative Counsel's CAML content files read by a tokenizer (caml_readers.reader_a); an independent xml.etree reading (caml_readers.reader_b) agrees on every section

This section cites

Provisions in this library that the text above cites, as it prints each citation. A range cited as “ss. 61.13-61.16” links its first and last provisions.

Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.