Pub. Contract Code, § 10843 · Article 8. Modifications; Performance; Payment

Pub. Contract Code, § 10843

Verbatim from the official edition

Text — As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)

If the trustees deem that a contractor has failed to supply an adequate working force, or material of proper quality, or has failed in any other respect to prosecute the work with the diligence and force specified by the contract, the trustees may:

(a) After written notice of at least five days to the contractor, specifying the defaults to be remedied, provide any such labor or materials and deduct the cost from any money due or to become due to the contractor under the contract; or

(b) If the trustees consider that the failure is sufficient ground for such action, they may give written notice of at least five days to the contractor and the contractor’s sureties, that if the defaults are not remedied the contractor’s control over the work will be terminated.

Notes and commentary — not statutory text

History

Added by Stats. 1984, Ch. 1128, Sec. 4.

Source of truth

Edition
As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
Official file
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PCC&sectionNum=10843.
Text hash
sha256 4de01fb3428c0c315112b4a231c51c9a72259d7333e153d5e4fade10bf9208dd
Composed by
compose_ca.py 2026-10-22: the Legislative Counsel's CAML content files read by a tokenizer (caml_readers.reader_a); an independent xml.etree reading (caml_readers.reader_b) agrees on every section

Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.