Pub. Contract Code, § 20102 · Article 1. Title
Pub. Contract Code, § 20102
Text — As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
Notwithstanding any other provision of this part to the contrary, where plans and specifications have been prepared by a public agency, whose activities are subject to this part, in order for a public project to be put out for formal or informal bid, and, subsequently, the public agency elects to perform the work by day’s labor, the public agency shall perform the work in strict accordance with these same plans and specifications.
Revisions of the plans and specifications may be made once a justification detailing the specific reasons for the change or changes has been approved by the public agency or its project director and a copy of the change and its justification is placed in the project file.
Notes and commentary — not statutory text
History
Amended by Stats. 1990, Ch. 694, Sec. 9.
Source of truth
- Edition
- As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
- Official file
- https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PCC§ionNum=20102.
- Text hash
- sha256 474842a10091dd5a2b5c04fd671c06417fcdbe9d2662a2e5ee2ff6c5cee4c3f2
- Composed by
- compose_ca.py 2026-10-22: the Legislative Counsel's CAML content files read by a tokenizer (caml_readers.reader_a); an independent xml.etree reading (caml_readers.reader_b) agrees on every section
Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.