Pub. Contract Code, § 22035 · Article 3. Public Projects: Alternative Procedure

Pub. Contract Code, § 22035

Verbatim from the official edition

Text — As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)

(a) In cases of emergency when repair or replacements are necessary, the governing body may proceed at once to replace or repair any public facility without adopting plans, specifications, strain sheets, or working details, or giving notice for bids to let contracts. The work may be done by day labor under the direction of the governing body, by contractor, or by a combination of the two.

(b) In case of an emergency, if notice for bids to let contracts will not be given, the public agency shall comply with Chapter 2.5 (commencing with Section 22050).

Notes and commentary — not statutory text

History

Repealed and added by Stats. 1994, Ch. 803, Sec. 87. Effective January 1, 1995.

Source of truth

Edition
As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
Official file
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PCC&sectionNum=22035.
Text hash
sha256 9368381c9e2f3db758dfd64dbf8f2d86f616916771bb546e4520626a9540d2fb
Composed by
compose_ca.py 2026-10-22: the Legislative Counsel's CAML content files read by a tokenizer (caml_readers.reader_a); an independent xml.etree reading (caml_readers.reader_b) agrees on every section

This section cites

Provisions in this library that the text above cites, as it prints each citation. A range cited as “ss. 61.13-61.16” links its first and last provisions.

Cited by 2 provisions

Provisions in this library whose text cites Pub. Contract Code, § 22035. Each shows the citation as that text prints it.

Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.