Skip to main content

Pub. Contract Code, § 6954 · Chapter 6.6. Alternative Project Delivery Program: Construction Manager/General Contractor Authority

Pub. Contract Code, § 6954

Verbatim from the official edition

Text — As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)

(a) If a contract for CMGC services is entered into pursuant to this chapter and includes preconstruction services by the construction manager, the San Diego Association of Governments shall enter into a written contract with the construction manager for preconstruction services, under which the San Diego Association of Governments shall pay the construction manager a fee for preconstruction services in an amount agreed upon by the San Diego Association of Governments and the construction manager. The preconstruction services contract may include fees for services to be performed during the contract period; provided, however, the San Diego Association of Governments shall not request or obtain a fixed price or a guaranteed maximum price for the construction contract from the construction manager or enter into a construction contract with the construction manager until after the San Diego Association of Governments has entered into a services contract. A preconstruction services contract shall provide for the subsequent negotiation for construction of all or any discrete phase or phases of the project and shall provide for the San Diego Association of Governments to own the design plans and other preconstruction services work product.

(b) A contract for construction services will be awarded after the plans have been sufficiently developed and either a fixed price or a guaranteed maximum price has been successfully negotiated. In the event that a fixed price or a guaranteed maximum price is not negotiated, the San Diego Association of Governments may award the contract for construction services utilizing any other procurement method authorized by law.

(c) The construction manager shall perform not less than 30 percent of the work covered by the fixed price or guaranteed maximum price agreement reached. Work that is not performed directly by the construction manager shall be bid to subcontractors pursuant to Section 6955.

Notes and commentary — not statutory text

History

Added by Stats. 2012, Ch. 767, Sec. 1. (SB 1549) Effective January 1, 2013.

Source of truth

Edition
As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
Official file
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PCC&sectionNum=6954.
Text hash
sha256 fef4da7ee502e8c8ed0177d4e6d7c353d874b1b54568470604d19926653ec649
Composed by
compose_ca.py 2026-10-22: the Legislative Counsel's CAML content files read by a tokenizer (caml_readers.reader_a); an independent xml.etree reading (caml_readers.reader_b) agrees on every section

This section cites

Provisions in this library that the text above cites, as it prints each citation. A range cited as “ss. 61.13-61.16” links its first and last provisions.

Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.