Pub. Contract Code, § 6972 · Chapter 6.7. Construction Manager/General Contractor Method: Regional Projects on Expressways

Pub. Contract Code, § 6972

Verbatim from the official edition

Text — As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)

(a) A regional transportation agency may utilize the Construction Manager/General Contractor method of procurement to design and construct projects pursuant to this section.

(b) A regional transportation agency may enter into a Construction Manager/General Contractor contract pursuant to this chapter after evaluation of the traditional design-bid-build method of construction and of the Construction Manager/General Contractor method and the board of the regional transportation agency affirmatively adopts the procurement strategy in a public meeting.

(c) The entity responsible for the maintenance of the local streets and roads within the jurisdiction of the expressway shall be responsible for the maintenance of the expressway.

Notes and commentary — not statutory text

History

Amended by Stats. 2016, Ch. 753, Sec. 3. (AB 2374) Effective January 1, 2017.

Source of truth

Edition
As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
Official file
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PCC&sectionNum=6972.
Text hash
sha256 02ea718d8c00b66119473b3a582b3a10a03b1cef04a958c11000efe248c43a5b
Composed by
compose_ca.py 2026-10-22: the Legislative Counsel's CAML content files read by a tokenizer (caml_readers.reader_a); an independent xml.etree reading (caml_readers.reader_b) agrees on every section

Cited by 1 provision

Provisions in this library whose text cites Pub. Contract Code, § 6972. Each shows the citation as that text prints it.

Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.