Except as provided in Section 25501, no construction of any thermal powerplant or electric transmission line shall be commenced by any electric utility without first obtaining certification as prescribed in this division. Any onsite improvements not qualifying as construction may be required to be restored as determined by the commission to be necessary to protect the environment, if certification is denied.

Notes and commentary — not statutory text

History

Amended by Stats. 1994, Ch. 1145, Sec. 14. Effective January 1, 1995.

Source of truth

Edition
As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
Official file
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PRC&sectionNum=25517.
Text hash
sha256 9b225614a8d05edc03b22a16ca7e301664a8af569da0dfb92fccbc7144433ecc
Composed by
compose_ca.py 2026-10-22: the Legislative Counsel's CAML content files read by a tokenizer (caml_readers.reader_a); an independent xml.etree reading (caml_readers.reader_b) agrees on every section

This section cites

Provisions in this library that the text above cites, as it prints each citation. A range cited as “ss. 61.13-61.16” links its first and last provisions.

Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.