Notwithstanding Section 2773.1, a surety bond that was executed by any personal surety that was approved by the lead agency prior to February 13, 1998, to ensure that reclamation is performed in accordance with a reclamation plan approved by a lead agency prior to that date, may be utilized to satisfy the requirements of this chapter, if the amount of the financial assurance required to perform the approved reclamation plan, as amended or updated from time to time, does not change from the amount approved prior to February 13, 1998.

Notes and commentary — not statutory text

History

Added by Stats. 1998, Ch. 643, Sec. 2. Effective January 1, 1999.

Source of truth

Edition
As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
Official file
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PRC&sectionNum=2773.15.
Text hash
sha256 040288b36692618ca836b800379805bc026585a78cfed51695458a37656c5d40
Composed by
compose_ca.py 2026-10-22: the Legislative Counsel's CAML content files read by a tokenizer (caml_readers.reader_a); an independent xml.etree reading (caml_readers.reader_b) agrees on every section

This section cites

Provisions in this library that the text above cites, as it prints each citation. A range cited as “ss. 61.13-61.16” links its first and last provisions.

Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.