(a) Notwithstanding any other provision of this article, and in addition to the requirements of Article 1 (commencing with Section 1001), an electrical corporation proposing to construct an electrical transmission line to the northwestern United States shall provide the commission with sufficient reliable information to enable the commission to determine that the proposed line, at the electric rates expected to prevail over the useful life of the line, will be cost effective. The commission, in its analysis of the forecast cost of electricity, shall take into consideration the recent increases in the charges for purchasing surplus electricity from the northwestern United States, the possibility of future increases in those charges, the feasibility of negotiating long-term contracts under reasonable charges, and the feasibility of purchasing electricity directly from Canada rather than through the Bonneville Power Administration.
(b) The commission shall not issue a certificate of public convenience and necessity unless it is satisfied that the electrical corporation has provided the information described in subdivision (a).
Notes and commentary — not statutory text
History
Added by Stats. 1986, Ch. 104, Sec. 1.
Source of truth
- Edition
- As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
- Official file
- https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PUC§ionNum=1102.
- Text hash
- sha256 6bf95c12077d16f424e3ad3e19ef224b274818a8eb0cce0dcdcd15cafb204bb3
- Composed by
- compose_ca.py 2026-10-22: the Legislative Counsel's CAML content files read by a tokenizer (caml_readers.reader_a); an independent xml.etree reading (caml_readers.reader_b) agrees on every section
This section cites
Provisions in this library that the text above cites, as it prints each citation. A range cited as “ss. 61.13-61.16” links its first and last provisions.