(a) Notwithstanding paragraph (1) of subdivision (b) and paragraph (2) of subdivision (j) of Section 399.20, a conduit hydroelectric facility with an effective capacity of up to four megawatts that otherwise meets the requirements of Section 399.20 shall be eligible for the standard contract or tariff established pursuant to subdivision (c) of Section 399.20 if the electric generation facility meets all the following additional requirements:

(1) It was operational as of January 1, 1990.

(2) It delivers no more than three megawatts to the grid at any time.

(3) It complies with the electrical corporation’s Electric Rule 21 tariff or other distribution access tariff.

(b) A facility meeting the requirements of subdivision (a) shall receive payment pursuant to paragraph (1) of subdivision (d) of Section 399.20, provided that no payment shall be made for any electricity delivered to the grid in excess of three megawatts at any time.

Notes and commentary — not statutory text

History

Added by Stats. 2016, Ch. 665, Sec. 1. (AB 1979) Effective January 1, 2017.

Source of truth

Edition
As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
Official file
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PUC&sectionNum=399.20.5.
Text hash
sha256 90d3dca776816b311d41c5e9b24f087b01ce176bc2f2e962389a9051d6d112db
Composed by
compose_ca.py 2026-10-22: the Legislative Counsel's CAML content files read by a tokenizer (caml_readers.reader_a); an independent xml.etree reading (caml_readers.reader_b) agrees on every section

This section cites

Provisions in this library that the text above cites, as it prints each citation. A range cited as “ss. 61.13-61.16” links its first and last provisions.

Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.