(a) (1) In order to ensure that prudent investments in energy efficiency continue to be made that produce cost-effective energy savings, reduce customer demand, and contribute to the safe and reliable operation of the electrical distribution grid, it is the policy of this state and the intent of the Legislature that the commission shall supervise the administration of cost-effective energy efficiency programs authorized pursuant to its statutory authority, including Sections 381, 381.1, 381.2, 381.5, 382, 384.5, 400, 454.5, 454.55, 454.56, 589, 701.1, 749, and 769, Article 10 (commencing with Section 890) of Chapter 4, and Chapter 6 (commencing with Section 2781) of Part 2.
(2) As used in this section, the term “energy efficiency” includes, but is not limited to, cost-effective activities to achieve peak load reduction that improve end-use efficiency, lower customers’ bills, and reduce system needs.
(b) (1) If a customer or contractor is the recipient of a rebate or incentive offered by a public utility for an energy efficiency improvement or installation of energy efficient components, equipment, or appliances in a building, the public utility shall provide the rebate or incentive only if the customer or contractor certifies that the improvement or installation has complied with any applicable permitting requirements, including any applicable specifications or requirements set forth in the California Building Standards Code (Title 24 of the California Code of Regulations), and, if a contractor performed the installation or improvement, that the contractor holds the appropriate license for the work performed.
(2) In addition to the requirements of paragraph (1), if a customer or contractor is the recipient of a rebate or incentive offered by a public utility for the purchase or installation of central air conditioning or a heat pump, and their related fans, the public utility shall provide the rebate or incentive only if the customer or contractor provides proof of permit closure. The public utility is not responsible for verifying the proof of permit closure documentation provided by the customer or contractor.
(3) This subdivision does not imply or create authority or responsibility, or expand existing authority or responsibility, of a public utility for the enforcement of the building energy and water efficiency standards adopted pursuant to subdivision (a) or (b) of Section 25402 of the Public Resources Code, or appliance efficiency standards and certification requirements adopted pursuant to subdivision (c) of Section 25402 of the Public Resources Code.
(4) This subdivision does not limit the authority of the commission to impose any additional requirements on a recipient of any rebate or incentive.
(c) The commission, in evaluating energy efficiency investments under its statutory authority, shall also ensure that local and regional interests, multifamily dwellings, and energy service industry capabilities are incorporated into program portfolio design and that local governments, community-based organizations, and energy efficiency service providers are encouraged to participate in program implementation where appropriate.
(d) The commission, in a new or existing proceeding, shall review and update its policies governing energy efficiency programs funded by utility customers to facilitate achieving the targets established pursuant to subdivision (c) of Section 25310 of the Public Resources Code. In updating its policies, the commission shall, at a minimum, do all of the following:
(1) Authorize market transformation programs with appropriate levels of funding to achieve deeper energy efficiency savings.
(2) Authorize pay for performance programs that link incentives directly to measured energy savings. As part of pay for performance programs authorized by the commission, customers should be reasonably compensated for developing and implementing an energy efficiency plan, with a portion of their incentive reserved pending post project measurement results.
(3) Authorize programs to achieve deeper savings through operational, behavioral, and retrocommissioning activities.
(4) Ensure that customers have certainty in the values and methodology used to determine energy efficiency incentives by basing the amount of any incentives provided by gas and electrical corporations on the values and methodology contained in the executed customer agreement. Incentive payments shall be based on measured results.
Notes and commentary — not statutory text
History
Amended by Stats. 2017, Ch. 561, Sec. 210. (AB 1516) Effective January 1, 2018.
Source of truth
- Edition
- As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
- Official file
- https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PUC§ionNum=399.4.
- Text hash
- sha256 ff2bc2e3916aaad1965556d225a8e0ab510fc0c00cc03dab1e4b2499a82c2901
- Composed by
- compose_ca.py 2026-10-22: the Legislative Counsel's CAML content files read by a tokenizer (caml_readers.reader_a); an independent xml.etree reading (caml_readers.reader_b) agrees on every section
This section cites
Provisions in this library that the text above cites, as it prints each citation. A range cited as “ss. 61.13-61.16” links its first and last provisions.
Public Resources Code
Public Utilities Code
- Pub. Util. Code, § 381Printed as Sections 381, 381.1, 381.2, 381.5, 382, 384.5, 400, 454.5, 454.55, 454.56, 589, 701.1, 749, and 769
- Pub. Util. Code, § 381.1Printed as Sections 381, 381.1, 381.2, 381.5, 382, 384.5, 400, 454.5, 454.55, 454.56, 589, 701.1, 749, and 769
- Pub. Util. Code, § 381.2Printed as Sections 381, 381.1, 381.2, 381.5, 382, 384.5, 400, 454.5, 454.55, 454.56, 589, 701.1, 749, and 769
- Pub. Util. Code, § 381.5Printed as Sections 381, 381.1, 381.2, 381.5, 382, 384.5, 400, 454.5, 454.55, 454.56, 589, 701.1, 749, and 769
- Pub. Util. Code, § 382Printed as Sections 381, 381.1, 381.2, 381.5, 382, 384.5, 400, 454.5, 454.55, 454.56, 589, 701.1, 749, and 769
- Pub. Util. Code, § 384.5Printed as Sections 381, 381.1, 381.2, 381.5, 382, 384.5, 400, 454.5, 454.55, 454.56, 589, 701.1, 749, and 769
- Pub. Util. Code, § 400Printed as Sections 381, 381.1, 381.2, 381.5, 382, 384.5, 400, 454.5, 454.55, 454.56, 589, 701.1, 749, and 769
- Pub. Util. Code, § 454.5Printed as Sections 381, 381.1, 381.2, 381.5, 382, 384.5, 400, 454.5, 454.55, 454.56, 589, 701.1, 749, and 769
- Pub. Util. Code, § 454.55Printed as Sections 381, 381.1, 381.2, 381.5, 382, 384.5, 400, 454.5, 454.55, 454.56, 589, 701.1, 749, and 769
- Pub. Util. Code, § 454.56Printed as Sections 381, 381.1, 381.2, 381.5, 382, 384.5, 400, 454.5, 454.55, 454.56, 589, 701.1, 749, and 769
- Pub. Util. Code, § 589Printed as Sections 381, 381.1, 381.2, 381.5, 382, 384.5, 400, 454.5, 454.55, 454.56, 589, 701.1, 749, and 769
- Pub. Util. Code, § 701.1Printed as Sections 381, 381.1, 381.2, 381.5, 382, 384.5, 400, 454.5, 454.55, 454.56, 589, 701.1, 749, and 769
- Pub. Util. Code, § 749Printed as Sections 381, 381.1, 381.2, 381.5, 382, 384.5, 400, 454.5, 454.55, 454.56, 589, 701.1, 749, and 769
- Pub. Util. Code, § 769Printed as Sections 381, 381.1, 381.2, 381.5, 382, 384.5, 400, 454.5, 454.55, 454.56, 589, 701.1, 749, and 769
Cited by 3 provisions
Provisions in this library whose text cites Pub. Util. Code, § 399.4. Each shows the citation as that text prints it.
Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.