Pub. Util. Code, § 8326 · Chapter 2. Decommissioning of Nuclear Facilities
Pub. Util. Code, § 8326
Text — As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
(a) Each electrical utility owning, in whole or in part, or operating a nuclear facility, located in California or elsewhere, shall provide a decommissioning cost estimate to the commission or the board for all nuclear facilities which shall include all of the following:
(1) An estimate of costs of decommissioning.
(2) A description of changes in regulation, technology, and economics affecting the estimate of costs.
(3) A description of additions and deletions to nuclear facilities.
(4) Upon request of the commission or the board, other information required by the Nuclear Regulatory Commission regarding decommissioning costs.
(b) The decommissioning costs estimate study shall be periodically revised in accordance with procedures adopted by the commission or the board pursuant to Section 8327.
Notes and commentary — not statutory text
History
Added by Stats. 1988, Ch. 1560, Sec. 5.
Source of truth
- Edition
- As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
- Official file
- https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PUC§ionNum=8326.
- Text hash
- sha256 becd3b9914b46b9ba807893fadc8f6a88109d7cf23b7fb8c0d3b982ee3043964
- Composed by
- compose_ca.py 2026-10-22: the Legislative Counsel's CAML content files read by a tokenizer (caml_readers.reader_a); an independent xml.etree reading (caml_readers.reader_b) agrees on every section
This section cites
Provisions in this library that the text above cites, as it prints each citation. A range cited as “ss. 61.13-61.16” links its first and last provisions.
Public Utilities Code
Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.