(a) It is the intent of the Legislature by enacting this chapter and of the people of California by approving the bond measure pursuant to this chapter to initiate the construction of a high-speed train system that connects the San Francisco Transbay Terminal to Los Angeles Union Station and Anaheim, and links the state’s major population centers, including Sacramento, the San Francisco Bay Area, the Central Valley, Los Angeles, the Inland Empire, Orange County, and San Diego consistent with the authority’s certified environmental impact reports of November 2005 and July 9, 2008.

(b) (1) Net proceeds received from the sale of nine billion dollars ($9,000,000,000) principal amount of bonds authorized pursuant to this chapter, upon appropriation by the Legislature in the annual Budget Act, shall be used for (A) planning and engineering for the high-speed train system and (B) capital costs, as described in subdivision (c).

(2) As adopted by the authority in May 2007, Phase 1 of the high-speed train project is the corridor of the high-speed train system between San Francisco Transbay Terminal and Los Angeles Union Station and Anaheim.

(3) Upon a finding by the authority that expenditure of bond proceeds for capital costs in corridors other than the corridor described in paragraph (2) would advance the construction of the system, would be consistent with the criteria described in subdivision (f) of Section 2704.08, and would not have an adverse impact on the construction of Phase 1 of the high-speed train project, the authority may request funding for capital costs, and the Legislature may appropriate funds described in paragraph (1) in the annual Budget Act, to be expended for any of the following high-speed train corridors:

(A) Sacramento to Stockton to Fresno.

(B) San Francisco Transbay Terminal to San Jose to Fresno.

(C) Oakland to San Jose.

(D) Fresno to Bakersfield to Palmdale to Los Angeles Union Station.

(E) Los Angeles Union Station to Riverside to San Diego.

(F) Los Angeles Union Station to Anaheim to Irvine.

(G) Merced to Stockton to Oakland and San Francisco via the Altamont Corridor.

(4) Nothing in this section shall prejudice the authority’s determination and selection of the alignment from the Central Valley to the San Francisco Bay Area and its certification of the environmental impact report.

(5) Revenues of the authority, generated by operations of the high-speed train system above and beyond operating and maintenance costs and financing obligations, including, but not limited to, support of revenue bonds, as determined by the authority, shall be used for construction, expansion, improvement, replacement, and rehabilitation of the high-speed train system.

(c) Capital costs payable or reimbursable from proceeds of bonds described in paragraph (1) of subdivision (b) include, with respect to the high-speed train system or any portion thereof, all activities necessary for acquisition of interests in real property and rights-of-way and improvement thereof; acquisition and construction of tracks, structures, power systems, and stations; acquisition of rolling stock and related equipment; mitigation of any direct or indirect environmental impacts of activities authorized by this chapter; relocation assistance for displaced property owners and occupants; other related capital facilities and equipment; and such other purposes related to the foregoing, for the procurement thereof, and for the financing or refinancing thereof, as may be set forth in a statute hereafter enacted. The method of acquisition of any of the foregoing may also be set forth in a statute hereafter enacted.

(d) Proceeds of bonds authorized pursuant to this chapter shall not be used for any operating or maintenance costs of trains or facilities.

(e) The State Auditor shall perform periodic audits of the authority’s use of proceeds of bonds authorized pursuant to this chapter for consistency with the requirements of this chapter.

Notes and commentary — not statutory text

History

Added by Stats. 2008, Ch. 267, Sec. 9. Approved in Proposition 1A at the November 4, 2008, election.

Source of truth

Edition
As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
Official file
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=SHC&sectionNum=2704.04.
Text hash
sha256 335260d923e50556b78aa41c122888740258d66d4b8e6ad03ffdc26276aa39db
Composed by
compose_ca.py 2026-10-22: the Legislative Counsel's CAML content files read by a tokenizer (caml_readers.reader_a); an independent xml.etree reading (caml_readers.reader_b) agrees on every section

This section cites

Provisions in this library that the text above cites, as it prints each citation. A range cited as “ss. 61.13-61.16” links its first and last provisions.

Cited by 9 provisions

Provisions in this library whose text cites Sts. & Hy. Code, § 2704.04. Each shows the citation as that text prints it.

Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.