(a) Except as provided in subdivision (b), an operator of a solid waste disposal site may submit a solid waste assessment questionnaire to the appropriate regional board at least 24 months prior to the site’s solid waste water quality assessment test due date as established pursuant to Section 13273. The regional board shall require the operator to submit any additional information, as needed, or require onsite verification of the solid waste assessment questionnaire data in order to render a decision pursuant to subdivision (c).

(b) Any solid waste disposal site which is larger than 50,000 cubic yards or is known or suspected to contain hazardous substances, other than household hazardous wastes, shall be prohibited from submitting a solid waste assessment questionnaire under this section.

(c) The regional board shall complete a thorough analysis of each solid waste assessment questionnaire submitted pursuant to this section by a date 18 months prior to the solid waste assessment test due date. Based upon this analysis, the regional board shall determine whether or not the site has discharged hazardous substances which will impact the beneficial uses of water. If the regional board determines that the site has not so discharged hazardous substances, the regional board shall notify the operator that the operator is not required to prepare a solid waste water quality assessment test pursuant to Section 13273.

(d) If the regional board does not make the determination specified in subdivision (c), the operator shall submit all, or a portion of, a solid waste water quality assessment test. The regional board shall notify the operator of this determination and indicate if all, or what portion of, a solid waste water quality assessment test shall be required. The operator shall submit the solid waste water quality assessment test, or a portion thereof, by the date established pursuant to Section 13273.

(e) The state board shall develop a solid waste assessment questionnaire and guidelines for submittal no later than three months after the effective date of this statute adding this section. The questionnaire shall contain, but not be limited to, a characterization of the wastes, size of the site, age of the site, and other appropriate factors.

(f) Those operators of solid waste disposal sites listed by the state board pursuant to Section 13273 in Rank 3 and seeking an exemption under this section shall submit their solid waste assessment questionnaire no later than July 1, 1988. If the regional board does not make the determination specified in subdivision (c), the regional board shall require the operator to submit all, or a portion of, a solid waste water quality assessment test by July 1, 1990.

Notes and commentary — not statutory text

History

Added by Stats. 1987, Ch. 932, Sec. 2. Effective September 22, 1987.

Source of truth

Edition
As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
Official file
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=WAT&sectionNum=13273.1.
Text hash
sha256 2cd1bc4e576045ddbc6b1fe662c2a716d75576b341ce7e23aa234c353bd397f1
Composed by
compose_ca.py 2026-10-22: the Legislative Counsel's CAML content files read by a tokenizer (caml_readers.reader_a); an independent xml.etree reading (caml_readers.reader_b) agrees on every section

This section cites

Provisions in this library that the text above cites, as it prints each citation. A range cited as “ss. 61.13-61.16” links its first and last provisions.

Cited by 2 provisions

Provisions in this library whose text cites Wat. Code, § 13273.1. Each shows the citation as that text prints it.

Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.