§ 366.057, Fla. Stat. · Chapter 366. PUBLIC UTILITIES
Retirement of electrical power plants.
Text — 2026 Florida Statutes
A public utility shall provide notice to the commission at least 90 days before the full retirement of an electrical power plant if the date of such retirement does not coincide with the retirement date in the public utility’s most recently approved depreciation study. No later than 90 days after such notice, the commission may schedule a hearing to determine whether retirement of the plant is prudent and consistent with the state’s energy policy goals in s. 377.601(2). At a hearing scheduled under this section, the utility shall present its proposed retirement date for the plant, remaining depreciation expense on the plant, any other costs to be recovered in relation to the plant, and any planned replacement capacity.
Notes and commentary — not statutory text
History
s. 5, ch. 2024-186.
Source of truth
- Edition
- 2026 Florida Statutes
- Official file
- https://www.leg.state.fl.us/Statutes/index.cfm?App_mode=Display_Statute&URL=0300-0399/0366/0366.html
- Text hash
- sha256 3d4e6449ae7e1d40f9ff2675ffc253c738e75fe0fd935c1bf0359fd9a2200e17
- Composed by
- compose_v2.py 2026-10-04: the Legislature's structured HTML read in document order; verify_v2.py's independent reading agrees character for character
- composed from the Legislature's structured HTML (one source of text; no PDF extraction); a second, independent reading of the same bytes agrees character for character
This section cites
Provisions in this library that the text above cites, as it prints each citation. A range cited as “ss. 61.13-61.16” links its first and last provisions.
The Florida Statutes
Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.