Tex. Gov't Code § 2260.051 · Subchapter B. NEGOTIATION OF CLAIM
CLAIM FOR BREACH OF CONTRACT; NOTICE.
Text — Current through the 89th 2nd Called Legislative Session, 2025
(a) A contractor may make a claim against a unit of state government for breach of a contract between the unit of state government and the contractor. The unit of state government may assert a counterclaim against the contractor.
(b) A contractor must provide written notice to the unit of state government of a claim for breach of contract not later than the 180th day after the date of the event giving rise to the claim.
(c) The notice must state with particularity:
(1) the nature of the alleged breach;
(2) the amount the contractor seeks as damages; and
(3) the legal theory of recovery.
(d) A unit of state government must assert, in a writing delivered to the contractor, any counterclaim not later than the 60th day after the date of notice under Subsection (b). A unit of state government that does not comply with this subsection waives the right to assert the counterclaim.
Notes and commentary — not statutory text
History
Added by Acts 1999, 76th Leg., ch. 1352, Sec. 9, eff. Aug. 30, 1999.
Amended by:
Acts 2005, 79th Leg., Ch. 988 (H.B. 1940), Sec. 3, eff. September 1, 2005.
Source of truth
- Edition
- Current through the 89th 2nd Called Legislative Session, 2025
- Official file
- https://statutes.capitol.texas.gov/Docs/GV/htm/GV.2260.htm
- Text hash
- sha256 c7bbe054be98dbdae08e33c2c10e95bc484fea8ea8011d3e2a0e6b5731627770
- Composed by
- compose_tx.py 2026-10-05: the Legislative Council's chapter files read in document order; verify_tx.py's independent reading (lxml DOM walk) agrees character for character
Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.