Tex. Gov't Code § 2269.255 · Subchapter F. CONSTRUCTION MANAGER-AT-RISK METHOD
PERFORMANCE OF WORK.
Text — Current through the 89th 2nd Called Legislative Session, 2025
(a) A construction manager-at-risk shall publicly advertise for bids or proposals and receive bids or proposals from trade contractors or subcontractors for the performance of all major elements of the work other than the minor work that may be included in the general conditions.
(b) A construction manager-at-risk may seek to perform portions of the work itself if:
(1) the construction manager-at-risk submits its bid or proposal for those portions of the work in the same manner as all other trade contractors or subcontractors; and
(2) the governmental entity determines that the construction manager-at-risk's bid or proposal provides the best value for the governmental entity.
Notes and commentary — not statutory text
History
Added by Acts 2011, 82nd Leg., R.S., Ch. 1129 (H.B. 628), Sec. 2.08, eff. September 1, 2011.
Redesignated from Government Code, Chapter 2267 by Acts 2013, 83rd Leg., R.S., Ch. 161 (S.B. 1093), Sec. 22.001(23), eff. September 1, 2013.
Source of truth
- Edition
- Current through the 89th 2nd Called Legislative Session, 2025
- Official file
- https://statutes.capitol.texas.gov/Docs/GV/htm/GV.2269.htm
- Text hash
- sha256 17d2b730374eb05d03228f114f5cd7efbff5f254d73cdb519f04254e5ce86bc0
- Composed by
- compose_tx.py 2026-10-05: the Legislative Council's chapter files read in document order; verify_tx.py's independent reading (lxml DOM walk) agrees character for character
Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.