Tex. Transp. Code § 223.2475 · Subchapter F. DESIGN-BUILD CONTRACTS
CHANGES TO DESIGN-BUILD TEAM.
Text — Current through the 89th 2nd Called Legislative Session, 2025
(a) A design-build contractor selected for a contract may not make changes to companies or entities identified as part of the design-build team in a response to a request for proposals unless an identified company or entity:
(1) is no longer in business, is unable to fulfill its legal, financial, or business obligations, or can no longer meet the terms of the teaming agreement proposed for the project with the design-build contractor;
(2) voluntarily removes itself from the team;
(3) fails to provide a sufficient number of qualified personnel to fulfill the duties identified during the proposal stage; or
(4) fails to negotiate in good faith in a timely manner in accordance with provisions established in the teaming agreement proposed for the project.
(b) If the design-build contractor makes design-build team changes in violation of Subsection (a), any cost savings resulting from the changes accrue to the department and not to the design-build contractor.
Notes and commentary — not statutory text
History
Added by Acts 2019, 86th Leg., R.S., Ch. 773 (H.B. 1542), Sec. 1, eff. September 1, 2019.
Source of truth
- Edition
- Current through the 89th 2nd Called Legislative Session, 2025
- Official file
- https://statutes.capitol.texas.gov/Docs/TN/htm/TN.223.htm
- Text hash
- sha256 1fbca669041d2b920b3be979fd9a0e21b18542fb7a0be76161b81ad08d023528
- Composed by
- compose_tx.py 2026-10-05: the Legislative Council's chapter files read in document order; verify_tx.py's independent reading (lxml DOM walk) agrees character for character
Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.