EARLY EFFECTIVE DATE OF RATE CHANGE.
Text — Current through the 89th 2nd Called Legislative Session, 2025
(a) For good cause shown, the regulatory authority may allow a rate change, other than a major change, to take effect:
(1) before the end of the 35-day period prescribed by Section 36.102; and
(2) under conditions the regulatory authority prescribes, subject to suspension as provided by this subchapter.
(b) The electric utility shall immediately revise its tariffs to include the change.
Notes and commentary — not statutory text
History
Acts 1997, 75th Leg., ch. 166, Sec. 1, eff. Sept. 1, 1997.
Source of truth
- Edition
- Current through the 89th 2nd Called Legislative Session, 2025
- Official file
- https://statutes.capitol.texas.gov/Docs/UT/htm/UT.36.htm
- Text hash
- sha256 348657fed87d80076085d729f3edf144424a35ef12929d75483ff0f64bddb19b
- Composed by
- compose_tx.py 2026-10-05: the Legislative Council's chapter files read in document order; verify_tx.py's independent reading (lxml DOM walk) agrees character for character
This section cites
Provisions in this library that the text above cites, as it prints each citation. A range cited as “ss. 61.13-61.16” links its first and last provisions.
Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.