Tex. Water Code § 57.117 · Subchapter D. POWERS AND DUTIES
INSPECTION AND REPORT BY EXECUTIVE DIRECTOR.
Text — Current through the 89th 2nd Called Legislative Session, 2025
(a) The executive director shall inspect the construction of a levee or other improvement once every 60 days after the construction work has commenced, and if he finds that the work has been done in strict accordance with the contract, the executive director shall certify this fact, and his certificate shall give a full description of the work done up to the date of inspection.
(b) If the executive director finds that the work has not been done in strict accordance with the contract, he shall officially certify this fact, and in the certificate he shall state where the contractor has failed to comply with the contract.
Notes and commentary — not statutory text
History
Acts 1971, 62nd Leg., p. 110, ch. 58, Sec. 1, eff. Aug. 30, 1971. Amended by Acts 1981, 67th Leg., p. 961, ch. 367, Sec. 1, eff. June 10, 1981; Acts 2003, 78th Leg., ch. 248, Sec. 40, eff. June 18, 2003.
Source of truth
- Edition
- Current through the 89th 2nd Called Legislative Session, 2025
- Official file
- https://statutes.capitol.texas.gov/Docs/WA/htm/WA.57.htm
- Text hash
- sha256 9f958a595bdbf8e6062e1acde9a4b0713c4ca68e3555ab2fa308aad892a5c49a
- Composed by
- compose_tx.py 2026-10-05: the Legislative Council's chapter files read in document order; verify_tx.py's independent reading (lxml DOM walk) agrees character for character
Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.