Skip to main content

Pub. Contract Code, § 10200 · Article 6.5. Department of Water Resources Design-Build Projects

Pub. Contract Code, § 10200

Verbatim from the official edition

Text — As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)

(a) The Legislature finds and declares that the design-build method of project delivery, using a best value procurement methodology, has been authorized for various agencies that have reported benefits from such projects including reduced project costs, expedited project completion, and design features that are not achievable through the traditional design-bid-build method.

(b) It is the intent of the Legislature that the following occur:

(1) This article provides specific authorization to the Department of Water Resources.

(2) This article shall not be deemed to provide a preference for the design-build method over other procurement methodologies.

Notes and commentary — not statutory text

History

Added by Stats. 2021, Ch. 247, Sec. 4. (SB 626) Effective January 1, 2022. Repealed as of January 1, 2033, pursuant to Section 10214.

Source of truth

Edition
As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
Official file
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PCC&sectionNum=10200.
Text hash
sha256 c1db8e1c8269fe84461d4242ca4c84e1fd6b3d506df1e5041d161db214f12632
Composed by
compose_ca.py 2026-10-22: the Legislative Counsel's CAML content files read by a tokenizer (caml_readers.reader_a); an independent xml.etree reading (caml_readers.reader_b) agrees on every section

Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.