Pub. Contract Code, § 10200.5 · Article 6.5. Department of Water Resources Design-Build Projects

Pub. Contract Code, § 10200.5

Verbatim from the official edition

Text — As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)

For purposes of this article, the following definitions and the definitions in subdivision (a) of Section 13332.19 of the Government Code shall apply:

(a) “Best value” means a value determined by evaluation of objective criteria that relate to price, features, functions, life-cycle costs, experience, and past performance. A best value determination may involve the selection of the lowest cost proposal meeting the interests of the department and meeting the objectives of the project, selection of the best proposal for a stipulated sum established by the procuring agency, or a tradeoff between price and other specified factors.

(b) “Construction subcontract” means each subcontract awarded by the design-build entity to a subcontractor that will perform work or labor or render service to the design-build entity in or about the construction of the work or improvement, or a subcontractor licensed by the State of California that, under subcontract to the design-build entity, specially fabricates and installs a portion of the work or improvement according to detailed drawings contained in the plans and specifications produced by the design-build team.

(c) “Department” means the Department of Water Resources.

(d) “Design-build” means a project delivery process in which both the design and construction of a project are procured from a single entity.

(e) “Design-build entity” means a corporation, limited liability company, partnership, joint venture, or other legal entity that is able to provide appropriately licensed contracting, architectural, and engineering services as needed pursuant to a design-build contract.

(f) “Design-build team” means the design-build entity itself and the individuals and other entities identified by the design-build entity as members of its team. Members shall include the general contractor and, if utilized in the design of the project, all electrical, mechanical, and plumbing contractors.

(g) “Director” means the Director of Water Resources.

Notes and commentary — not statutory text

History

Added by Stats. 2021, Ch. 247, Sec. 4. (SB 626) Effective January 1, 2022. Repealed as of January 1, 2033, pursuant to Section 10214.

Source of truth

Edition
As published in the Legislative Counsel's database, tables dated October 18, 2026 (pubinfo_2025.zip)
Official file
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PCC&sectionNum=10200.5.
Text hash
sha256 243b442ae5cd0dcb35cf9f583cfac1386e8da330e91a53b0d3ee7dd1c86f5388
Composed by
compose_ca.py 2026-10-22: the Legislative Counsel's CAML content files read by a tokenizer (caml_readers.reader_a); an independent xml.etree reading (caml_readers.reader_b) agrees on every section

This section cites

Provisions in this library that the text above cites, as it prints each citation. A range cited as “ss. 61.13-61.16” links its first and last provisions.

Procedural information only. Not legal advice and not a substitute for the advice of an attorney. Confirm the current text with the official publisher before relying on it.